Lower Basin Water Treatment Plant

Town of Eagle Water News - Lower Basin Water Treatment Plant

Project Update 10/04/2018

PROJECT UPDATE SUMMARY

  • Installed dewatering wells – total of eight
  • Installed primary power system with transformer and activated service. This system will be used for construction power
  • Installed temporary power panels for dewatering system and construction power
  • Relocated sanitary sewer on the south side of the new Water Treatment Building
  • Mobilized excavation equipment and crew for earthwork
  • Began excavation for the Water Treatment Building
  • Removed sludge from Existing Lagoon area

PLANNED ACTIVITIES FOR THE NEXT 4 WEEKS:

  • Continue excavation for Water Treatment Building foundation
  • Excavate for Raw Water Pump Station Building
  • Install soil nail wall (shoring) for lower Water Treatment Building excavation area
  • Excavate for Raw Water Pump Station foundation
  • Form, rebar, place and finish Raw Water Pump Station slab on grade

Watch Presentation to Learn More